Scope of Work

 • Complete design of four 33kV/11kV electrical substations

 • Detailed engineering for equipment layout and cable routing

 • Design of structural supports and electrical components

 • Procurement and installation of all major electrical systems

 • Installation of emergency diesel generators

 • Installation of high-voltage (HV) and low-voltage (LV) switchboards

 • Installation of motor control centers (MCCs)

 • Installation of transformers and gas-insulated switchgear (GIS)

 • Installation of capacitor banks, UPS units, and battery systems

 • Laying and termination of over 1.5 million meters of electrical cables

 • Setup of integrated communication systems

 • Installation of fire alarm systems

 • Delivery of critical power infrastructure to support industrial operations in Iraq for Samsung